Australian Standards for prefab buildings

The editions listed here are those in the NCC 2022 schedule of referenced documents. NCC 2025 has been published, but "published" is not "in force": each state and territory sets its own start date, set out in [NCC 2025 and new homes](/guides/ncc-2025-new-homes-what-changes/). The NCC 2025 schedule was not compiled for this page, so editions may differ where NCC 2025 applies.
Standards and the NCC
Where listedNCC Schedule 2, referenced documents[1]
Edition ruleOnly the edition named in the schedule has standing under the NCC[1]
Framing (timber)AS 1684.2-2021, non-cyclonic areas[2]
Wind loads, housingAS 4055-2021[2]
Slabs and footingsAS 2870-2011[2]

A prefab home is built to the same technical rules as a site-built one, and those rules mostly sit in Australian Standards that the National Construction Code (NCC) points to rather than reproduces.[1] This page indexes the standards named in the NCC 2022 schedule of referenced documents by the part of a building they concern, with the edition the schedule adopts. It is an index, not a summary of what any standard requires.

How the NCC uses standards §

The NCC lists the standards it relies on in a schedule of referenced documents. That schedule applies to the Deemed-to-Satisfy Provisions, Specifications and Verification Methods, and a listed document applies only to the provision that cites it.[1] The schedule names an exact edition, and other editions have no standing under the NCC; a Performance Solution, however, may use any document or edition that helps meet the Performance Requirements.[1]

The practical consequence is that a standard number alone is not enough to describe a requirement: the edition year matters. For example, the timber-framing standard AS 1684.2 was updated to a 2021 edition that replaced the 2010 edition as the referenced document in NCC 2022.[3]

Structure and framing §

TopicStandardEdition
Timber framing, non-cyclonicAS 1684 Part 22021[2]
Timber framing, cyclonicAS 1684 Part 32021[2]
Timber framing, simplifiedAS 1684 Part 42010[2]
Timber structures, designAS 1720 Part 12010[2]
Nailplated roof trussesAS 1720 Part 52015[2]
Steel structuresAS 41002020[2]
Cold-formed steelAS/NZS 46002018[2]
Concrete structuresAS 36002018[2]
Masonry structuresAS 37002018[2]
Reinforced AAC structuresAS 5146 Part 12015[2]

The NCC 2022 schedule also lists the NASH Standard documents on residential and low-rise steel framing (Part 1 dated 2005, Part 2 dated 2014) and a 2021 NASH Standard for steel framed construction in bushfire areas.[2] How these framing systems compare in prefab is covered in timber framing and engineered wood, steel framing and precast concrete homes.

Loads, wind, soil and footings §

TopicStandardEdition
Structural actions, generalAS/NZS 1170 Part 02002[2]
Permanent and imposed actionsAS/NZS 1170 Part 12002[2]
Wind actionsAS/NZS 1170 Part 22021[2]
Snow and ice actionsAS/NZS 1170 Part 32003[2]
Earthquake actionsAS 1170 Part 42007[2]
Wind loads for housingAS 40552021[2]
Residential slabs and footingsAS 28702011[2]
PilingAS 21592009[2]
Earth-retaining structuresAS 46782002[2]

Wind classification is explained in cyclonic and high-wind regions, and the soil classification that AS 2870 works from is in site classification and soil reactivity. Foundations for factory-built homes are in modular home foundations.

Fire, bushfire and smoke alarms §

TopicStandardEdition
Bushfire-prone constructionAS 39592018[2]
Fire resistance testsAS 1530 Part 42014[2]
Bushfire exposure testsAS 1530 Part 8.12018[2]
Combustibility testAS 1530 Part 11994[2]
Smoke alarmsAS 37862014[2]
Home fire sprinklersAS 2118 Part 52008 (R 2020)[2]
Wall and ceiling liningsAS 5637 Part 12015[2]

The bushfire standard feeds the attack-level system described in bushfire attack levels and prefab homes. The AS 2118 Part 4 sprinkler standard for accommodation buildings (2012) also appears in the schedule.[2] Which buildings must have sprinklers or alarms depends on the building class; see building classes for shared housing.

Wet areas, moisture and the building envelope §

TopicStandardEdition
Waterproofing of wet areasAS 37402021[2]
Wet area membranesAS/NZS 48582004[2]
External membranes, designAS 4654 Part 22012[2]
Windows and glazed doorsAS 20472014[2]
Glass in buildingsAS 12882021[2]
Thermal insulation, generalAS/NZS 4859 Part 12018[2]
Pliable membranes, materialsAS 4200 Part 12017[2]
Metal roof and wall claddingAS 1562 Part 12018[2]
Termite managementAS 3660 Part 12014[2]

Because bathroom pods are built and waterproofed off site, the wet-area standards are relevant to them; see bathroom pods.

Plumbing, drainage and services §

TopicStandardEdition
Water servicesAS/NZS 3500 Part 12018 and 2021 both listed[2]
Sanitary plumbing and drainageAS/NZS 3500 Part 22021[2]
Stormwater drainageAS/NZS 3500 Part 32021[2]
Heated water servicesAS/NZS 3500 Part 42021[2]
On-site wastewater managementAS/NZS 15472012[2]
Gas installationsAS/NZS 5601 Part 12013[2]

The schedule lists two editions of AS/NZS 3500 Part 1, which is one reason the edition named by the specific NCC provision matters.[2] Plumbing practice in factory settings is covered in plumbing in factory-built homes.

Access and other standards §

The NCC 2022 schedule lists AS 1428 Part 1 in two editions (2009 and 2001) and the ABCB Livable Housing Design standard (2022).[2] The ABCB also publishes the Housing Provisions Standard (2022) and a standard for construction in flood hazard areas (2012, version 2012.3), both in the same schedule.[2] See the Livable Housing Design Standard for that standard.

Imported and certified products §

Standards also come up where a home is imported or where a manufacturer's process is certified. Those are covered in imported prefab kits: what compliance requires and who inspects and certifies a factory-built home.

What is not covered here §

This page is a topic index drawn from the NCC 2022 Volume Two schedule of referenced documents. It is not a complete list of the 166 entries, and it does not state what any standard requires.

It does not cover the NCC 2025 schedule, so it does not show which editions changed. It does not cover Volume One (Class 2 to 9) schedules separately, state and territory variations to the referenced documents, or standards used only by a Performance Solution.

Electrical installation wiring rules do not appear in the compiled schedule extract; see electrical work in factory-built homes. Standards Australia catalogue entries, current amendments, prices and whether a standard has been withdrawn or reissued are not covered by sources compiled here. Standards are copyright documents and the text itself is not reproduced.

Which standards apply to a given building is decided by the building surveyor or certifier. Nothing here is compliance advice.

Ask Modular Living AI about this guide

Still have a question after reading this guide? Ask it here. The answer draws on this guide, our other guides and the official pages they cite, with links to each one it used.

General information only, not legal, financial or building advice.

The Dispatch — a monthly email when new guides are published. No noise; unsubscribe anytime.

Sent to info@modularlivingaustralia.com.au and handled by a person. See Privacy.

References §

  1. Australian Building Codes Board — NCC 2022 Volume Two, Part A4 Referenced documents — The NCC refers to other documents, including Australian Standards, for requirements it does not set out itself. Primary referenced documents are listed in Schedule 2; secondary ones are those cited by a primary document. Schedule 2 is mandatory only for Deemed-to-Satisfy Provisions, Specifications and Verification Methods, and a referenced document applies only to the provision that cites it. Schedule 2 names the adopted edition, with any amendments considered appropriate, and other editions have no standing under the NCC. A secondary document is the edition current when the primary document was published. A Performance Solution may draw on any document or edition that helps meet the Performance Requirements. ncc.abcb.gov.au/editions/ncc-2022/adopted/volume-two/a-governing-requirements/part-a4-referenced-documents
  2. Australian Building Codes Board — NCC 2022 Volume Two, Schedule 2 Referenced documents — Table of 166 referenced-document rows giving standard number, edition year and title, including AS 1684 Parts 2, 3 and 4; AS 1720 Parts 1, 4 and 5; AS/NZS 1170 Parts 0 to 3 and AS 1170 Part 4; AS 2870; AS 3600; AS 3660 Parts 1 and 3; AS 3740; AS 3959; AS 4055; AS 4100; AS/NZS 4600; AS 1530 Parts 1 to 4 and 8.1; AS 3786; AS/NZS 3500 Parts 0 to 4; AS/NZS 1547; AS 2047; AS 1288; AS/NZS 4859 Parts 1 and 2; AS 4200 Parts 1 and 2; AS 1562 Part 1; AS/NZS 4505. Also lists non-Standards Australia documents such as NASH Standard steel framing documents and ABCB publications. abcb.gov.au/editions/ncc-2022/adopted/volume-two/2-referenced-documents/referenced-documents
  3. Standards Australia — NCC 2022 standards spotlight: residential timber framed construction — AS 1684.2:2021, Residential timber-framed construction, Part 2: Non-cyclonic areas, is referenced in both Volume One and Volume Two of NCC 2022 and supersedes AS 1684.2-2010 as the primary referenced document. standards.org.au/blog/ncc-2022-standards-spotlight-residential-timber-framed-construction

Figures are as published by the sources above at their respective dates and are paraphrased summaries, not verbatim reproductions. Verify current pricing and rules directly with builders, lenders and planning authorities.