Modular construction for healthcare
| NCC class | Class 9a covers health-care buildings, generally hospitals[1] |
|---|---|
| WA modular wards (2022) | Four sites adding 120 beds, announced as the first of their kind for the state[2] |
| WA Albany (2026) | A 32-bed modular ward, with components built off site[3] |
| Queensland Gladstone | A 40-bed modular hospital, construction expected to finish by mid-2027[4] |
Hospitals and clinics are among the most heavily regulated buildings, yet several Australian state health agencies now describe wards and whole facilities as modular, with sections built off site and joined to existing hospitals. This page summarises what official pages say about those projects and where the National Construction Code places such buildings. It is a companion to modular construction for schools, and the NDIS-related housing side is in NDIS SDA housing and modular construction.
How the NCC classifies health buildings §
| Class | Covers | Example |
|---|---|---|
| 9a | Health-care buildings[1] | Hospital ward |
| 5 | Usually a GP's rooms[1] | Medical office |
| 8 | Usually a laboratory[1] | Stand-alone lab |
The ABCB explains that Class 9a generally means hospitals, where patients are treated and may need help to evacuate. It also reaches clinics and day surgeries where treatment can leave patients unable to move. A laboratory inside a health-care building is classed 9a rather than 8.[1] Class 9c, for residential aged care, is covered in building classes for shared housing. Whether a particular building is modular does not change its class; the class follows its use.
Western Australia: modular wards from 2022 §
In June 2022 the WA Government announced modular wards at four general hospitals (Osborne Park, Rockingham, Bentley and Bunbury), describing them as the first of their kind for the state. Together they add 120 beds, each ward taking low-to-medium acuity patients so that acute beds are freed. The statement says Osborne Park reached practical completion after just over six months of building and credits modular construction plus a fast-tracked approvals process for the speed.[2] Bentley's 30-bed ward opened on 11 October 2022.[5] The statement names Multiplex as builder and gives no cost.[2]
Western Australia: Albany and Meekatharra §
An August 2026 statement says Hutchinson Builders won a combined design and construct contract for Albany Health Campus and Meekatharra Hospital. Modular components are to be built off site, transported and assembled, with the stated aim of shortening build times and limiting disruption to hospital operations. Albany's element is a 32-bed modular ward. The statement lists project figures of $60 million for Albany and $73.4 million for Meekatharra, and gives no construction dates.[3] These are government-stated project budgets, not outcomes.
Queensland: Gladstone modular hospital §
Central Queensland Health describes a purpose-built modular hospital at Gladstone, connected to the existing hospital, with 40 inpatient beds, a five-bed high dependency unit and six dialysis chairs across more than 2,500 square metres. It gives construction as expected to finish by mid-2027 and states its purpose as meeting demand and addressing ageing infrastructure.[4]
Comparison of the projects §
| Project | Scale | Stated timing |
|---|---|---|
| WA four-site wards | 120 beds[2] | Opened 2022[5] |
| Albany ward | 32 beds[3] | No dates given[3] |
| Gladstone | 40 beds[4] | Mid-2027 expected[4] |
The pages differ in detail, so the table should not be read as a like-for-like comparison of cost or speed. No cost per bed is given in any of them.
What is not covered here §
- Other states and territories (NSW, Victoria, South Australia, Tasmania, ACT, NT): not covered by sources compiled here.
- Independent evidence on cost, time savings or clinical outcomes of modular health buildings: not covered by sources compiled here.
- Health-specific NCC and state design guidelines beyond the Class 9a definition: not covered by sources compiled here.
- Projects described only by builder or supplier websites: not covered by sources compiled here.
Ask Modular Living AI about this guide
Still have a question after reading this guide? Ask it here. The answer draws on this guide, our other guides and the official pages they cite, with links to each one it used.
General information only, not legal, financial or building advice.
Sent to info@modularlivingaustralia.com.au and handled by a person. See Privacy.
References §
- Australian Building Codes Board — Understanding the NCC: building classifications — Class 9a covers health-care buildings, generally hospitals, where patients receive treatment and may need physical help to evacuate. It includes clinics and day surgeries where treatment can leave patients unconscious or unable to move. A general practitioner's rooms are usually Class 5 unless treatment can leave patients in that state. Laboratories are usually Class 8 but are Class 9a when part of a health-care building. nccb.gov.au/sites/default/files/resources/2022/UTNCC-Building-classifications.PDF
- Government of Western Australia — Innovative modular hospital wards to boost WA's hospital capacity (media statement, 28 June 2022) — Describes modular wards at Osborne Park, Rockingham, Bentley and Bunbury hospitals as the first of their kind for the state. Osborne Park is a 30-bed ward; the four sites together add 120 beds. Each ward has 10 single and 10 double rooms, a gymnasium, therapy pod and dining room, connected to the existing hospital. The wards take low-to-medium acuity patients. Osborne Park reached practical completion on 1 July 2022 after just over six months of building. The government credits modular construction with a fast-tracked approvals process. Multiplex built the wards. No cost is stated on the page. wa.gov.au/government/media-statements/McGowan%20Labor%20Government/Innovative-modular-hospital-wards-to-boost-WA's-hospital-capacity-20220628
- Government of Western Australia — Design and construct contract awarded for Meekatharra Hospital and Albany Health Campus (media statement, 18 August 2026) — Hutchinson Builders won the design and construct contract for both projects. Modular components are to be built off site and assembled at the hospitals, with the stated aim of shortening build times and limiting disruption. Albany is a new 32-bed modular ward; Meekatharra includes a new emergency department, a five-bed acute inpatient unit, a palliative care suite and renal dialysis. Stated project figures are $60 million (Albany) and $73.4 million (Meekatharra). No construction dates are given. wa.gov.au/government/media-statements/Cook%20Labor%20Government/Design-and-construct-contract-awarded-for-Meekatharra-Hospital-and-Albany-Health-Campus-20260818
- Central Queensland Hospital and Health Service — New modular hospital to support future care at Gladstone Hospital — A purpose-built modular hospital on the Gladstone Hospital campus, connected to the existing hospital. It has 40 inpatient beds (including palliative care, bariatric and isolation rooms), a five-bed high dependency unit and six renal dialysis chairs, with more than 2,500 square metres of clinical space. Construction is expected to finish by mid-2027. No cost is stated. cq.health.qld.gov.au/about-us/news/new-modular-hospital-to-support-future-care-at-gladstone-hospital
- Government of Western Australia — Bentley Hospital's new modular beds now open (media statement, 11 October 2022) — A 30-bed modular ward at Bentley Hospital, with 10 single and 10 double rooms each with its own bathroom, opened on 11 October 2022 and received its first patients from Royal Perth Hospital. The government credits modular construction and fast-tracked approvals for the shorter build time. wa.gov.au/government/media-statements/McGowan%20Labor%20Government/Bentley-Hospital's-new-modular-beds-now-open-20221011
Figures are as published by the sources above at their respective dates and are paraphrased summaries, not verbatim reproductions. Verify current pricing and rules directly with builders, lenders and planning authorities.