Main page › Guides › Service connections
Connecting water, power and wastewater
| Wastewater standard | AS/NZS 1547, referenced by the PCA[1][2] |
|---|---|
| NSW wastewater approval | Section 68, Local Government Act 1993[2][3] |
| NSW secondary treatment | Must be accredited by NSW Health[3][4] |
| Electricity — basic connection | Often free where no network upgrade is needed (Energex)[5] |
| Electricity — who sets the fee | The distributor, not the retailer[6] |
| Complex connection assessment (TAS) | Non-refundable fee from A$2,603.24[7] |
| Off-grid | Solar, battery and rainwater in place of grid connections[8] |
| *Service connection costs are highly site-specific. No single national figure applies; confirm with the network and council for the address. | |
On-site wastewater systems are designed to AS/NZS 1547, and in New South Wales installing one needs council approval under section 68 of the Local Government Act 1993.[1][2][3] Electricity connection fees are set by the distributor rather than the retailer, and Energex states that a basic connection needing no network upgrade is often free; builder-published commercial guidance puts water, sewer, power and telecommunications connections at about A$7,600–A$30,600 in total.[5][6][8]
A serviced suburban block hides how much work "connecting services" actually is, because the work is already done: water, sewer, power and telecommunications are stubbed to the boundary. Move that same house to an infill block on an old septic system, or to acreage with no mains at all, and three separate approval-and-connection processes appear, each run by a different authority.
This is where a modular build's site budget most often blows out, and it is covered separately here from the broader site works costs because the rules — as opposed to the prices — are specific and knowable in advance.
Builder-published guidance puts service connections at roughly A$7,600 to $30,600 depending on location, with rural septic systems commonly A$15,300 to $38,200.[8] Those are commercial figures spanning an enormous range, because the answer depends almost entirely on the block.
Wastewater: the approval most people underestimate §
If a block is not connected to mains sewer, the wastewater system needs its own council approval — and that approval is frequently the critical-path item, not the building approval.
The national framework is AS/NZS 1547 (on-site domestic wastewater management), supported by the AS/NZS 1546 series for treatment units and AS/NZS 3500 for plumbing and drainage.[1] Each state overlays its own legislation, so the process differs by jurisdiction.
New South Wales
Any on-site treatment system requires council approval under Section 68 of the Local Government Act 1993 and the Local Government (General) Regulation 2021.[2][3] There is a distinctive extra step: NSW Health accredits the design of domestic sewage systems before a council can approve installation, and secondary treatment systems such as aerated wastewater treatment systems (AWTS) must be on that accredited list.[3][4]
NSW approvals also do not last forever. On-site systems are often given operational approvals that require periodic renewal, with some councils renewing every three to five years.[4] This is an ongoing obligation, not a one-off permit.
Queensland
A plumbing and drainage application is lodged with the council, and the council plumbing inspector reviews it against the Queensland Plumbing and Wastewater Code and the relevant Australian Standards. For a standard septic system with trench or bed disposal, no separate state-level tank approval is needed beyond the council plumbing permit.[4]
The common process
Across states, the sequence is broadly consistent:
- A site and soil evaluation assesses the land's capacity to absorb effluent.[9]
- A designer produces a system design showing tank location and specifications, the land application area, and load calculations demonstrating compliance with AS/NZS 1547.[9]
- An application — often titled "Application to Install a Human Waste Treatment Device" or similar — is lodged with the council, together with the soil report and design plans.[9]
- Council environmental health officers review it against state legislation, local bylaws and the standard, a process that can take several weeks to months.[2]
- A "Permit to Install" is issued, sometimes with conditions such as an ongoing maintenance or service contract.[2][3]
The soil's absorption capacity determines the size of the land application area, which in turn can determine whether a given system fits the block at all. On a small or poorly draining lot, this is a genuine design constraint, not a formality.
Electricity: the fee is smaller than the myth, but the connection can be large §
Two different things get called the "connection cost," and conflating them causes most of the confusion.
Putting your name on an existing meter. Where a house is already wired to the grid, the connection fee is essentially a metering-service charge to register the account.[6] Commercial guidance puts this initial charge in the range of A$10 to $60, alongside a daily network charge of around A$1.[10] It is payable even if the home has solar and a feed-in tariff.[6]
Physically extending the network to an unconnected block. This is the number that matters for a new or rural build, and it is set by the distributor — the business that transports energy — not the retailer that sells the plan.[6] Charges are regulated by the Australian Energy Regulator.[5]
The distributor's own framing is useful. Energex states that basic connections requiring no upgrade or change to the network — most homes, solar under 10 kW, batteries and small businesses — are generally free of charge, and distinguishes these "Standard Control Services" from "Alternative Control Services" such as negotiated connections and asset relocations, which incur a fee.[5]
The word doing the work is "basic." A block that needs new poles, a longer service run or a network upgrade moves into the negotiated, chargeable category. TasNetworks illustrates the mechanism: for large connections over 100 amps or complex projects, a non-refundable assessment fee of at least A$2,603.24 (incl. GST) may be required before you even receive a firm offer, with design costs then deducted from the final contribution.[7] Its published schedule lists discrete items — creation of a National Metering Identifier at A$49.23 (ex GST), crossover poles with overhead or underground service, and so on — that assemble into the total for a given site.[11]
The practical point: there is no national figure. The distributor for the address issues a site-specific offer, and where poles or a network extension are involved, that offer can dwarf every other line on this page. It is worth requesting before committing to a block.
Water and telecommunications §
Mains water connection charges are set by the local water authority and vary by network; no single figure applies, and they are bundled into the A$7,600–$30,600 service-connection range in commercial guidance rather than broken out.[8] Where there is no mains water, rainwater tanks become the supply — and in bushfire-prone areas a minimum tank capacity may be a condition of approval, a point covered under bushfire attack levels.
Telecommunications connection is generally arranged through the national broadband network for the premises. It is not covered in detail by the sources compiled here.
When off-grid is the answer §
On a remote block, the cost of extending the grid can exceed the cost of not using it. This is why so many rural modular builders offer off-grid packages: solar generation, battery storage and rainwater harvesting replace the mains connections entirely, and an on-site wastewater system was going to be required regardless.
Several builders in Australian directories describe off-grid capability as standard or optional. That is a commercial offering rather than a regulatory category — but the underlying logic is sound. Where a distributor's connection offer runs into the tens of thousands, the comparison is not "off-grid versus free grid power"; it is "off-grid system cost versus grid connection cost," and on a sufficiently remote block the former can win.
The wastewater approval process above still applies to an off-grid home. Going off-grid removes the electricity and water connections; it does not remove the Section 68 (or equivalent) wastewater approval.
What this page does not cover §
State-specific mains water and sewer connection charges, and the detailed wastewater approval processes for Victoria, South Australia, Western Australia, Tasmania, the ACT and the Northern Territory, are not set out in full here; the controlling documents are each state's on-site wastewater guideline and each council's requirements. Victoria's is published by EPA Victoria.[1]
The Australian Standards themselves — AS/NZS 1547, the AS/NZS 1546 series and AS/NZS 3500 — are copyright documents available through Standards Australia and are not reproduced here.[1]
Connection charges quoted above are indicative and, in the case of the commercial ranges, not independent survey data. The distributor and the council for a specific address are the only reliable sources for that address.
Sent to info@modularlivingaustralia.com.au and handled by a person. See Privacy.
References §
- EPA Victoria — Guideline for onsite wastewater management, May 2024 — Australian Standard AS/NZS 1547 On-site domestic wastewater management applies, alongside AS/NZS 1546 series for treatment units and AS/NZS 3500 for plumbing and drainage. An application must be referred to the EPA and the relevant water, drainage or sewerage authority in defined circumstances. Australian Standards can be purchased from the Standards Australia store. epa.vic.gov.au/sites/default/files/epa/publications/onsite-wastewater-management-pdf.pdf
- Imagine Kit Homes — Owner-builder's guide to septic and on-site wastewater systems — AS/NZS 1547 provides the national framework, but each state and territory has specific legislation and regulatory bodies that overlay it, dictating application processes, allowable system types, minimum treatment levels, setback distances and maintenance. In NSW, local councils administer approvals under the Local Government Act 1993 and the Protection of the Environment Operations Act 1997, and a Section 68 approval is typically required; council environmental health officers review applications against state legislation, local bylaws and AS/NZS 1547, a process that can take several weeks to months, after which a 'Permit to Install' is issued. Builder-published commercial guidance. imaginekithomes.com.au/guides/owner-builder-s-guide-to-septic-on-site-wastewater-systems-in-australia-mm9fdv9v/
- Eco Wastewater Treatment — Domestic wastewater treatment plant regulations in Australia — in NSW any on-site treatment plant requires approval from the local council under Section 68 of the Local Government Act 1993 and the Local Government (General) Regulation 2021, and NSW Health accredits the design of domestic sewage systems before councils can approve installation. Councils verify that the treatment unit is sized for the household, the land application area is adequate for the soil capacity, and the system type is approved for use in the state; they may impose conditions such as ongoing maintenance schedules or service contracts, then issue a Permit to Install or Construct. Commercial guidance. ecowastewatertreatment.com.au/domestic-wastewater-treatment-plant-regulations-in-australia-complete-compliance-guide/
- Eco Septic Tank — Septic tank permit guide for Australia — an application for plumbing and drainage work is lodged with the local council, typically by a licensed plumber or building certifier. In NSW, systems must comply with NSW Health guidelines and AS/NZS 1547, secondary treatment systems such as aerated wastewater treatment systems must be accredited by NSW Health, and on-site systems are often given operational approvals that require periodic renewal, with some councils renewing every three to five years. In Queensland the council plumbing inspector reviews plans against the Queensland Plumbing and Wastewater Code and AS/NZS 1547 and the AS/NZS 1546 series; for standard septic systems no separate state-level tank approval is needed beyond the council plumbing permit. Tasmania maintains an approved list of septic and treatment products. Commercial guidance. ecoseptictank.com.au/septic-tank-permit/
- Energex — Connection charges — what Energex charges for customer connection services is controlled by the Australian Energy Regulator. Basic connections that do not require upgrades or changes to the network — most homes, solar systems under 10 kW, batteries and small businesses — are generally free of charge. The AER classifies regulated distribution services into Standard Control Services (basic connections, some metering, network maintenance) and Alternative Control Services (negotiated connections, asset relocations and specific customer-requested services that incur a fee). energex.com.au/our-services/connections/residential-and-commercial-connections/connection-charges
- iSelect — Electricity connection fees by state and distributor — where a house is already wired to the grid, the connection fee is essentially a metering service cost to put the account holder's name on the meter, payable even with solar and a feed-in tariff. The fee depends on the energy distributor (the business that transports the energy) rather than the retailer (the business that sells the plan); Australia has only a handful of distributors, each with its own fees. Commercial comparison-site guidance. iselect.com.au/energy/electricity-connection-fees/
- TasNetworks — New electricity connections — a quote (letter of offer) is provided after network assessment and design. In most cases payment of estimated design costs is required after the application is processed, based on the work required to provide a connection offer. For large connections over 100 amps or complex projects, a non-refundable assessment fee of at least A$2,603.24 including GST may be required. Design costs are deducted from the contribution in the letter of offer; if the offer is not taken up, design costs and application fees are not refunded except for unused funds. Where underground consumer mains will cross public land, evidence of landowner approval must be provided before submitting the application. Network-operator published information. tasnetworks.com.au/new-electricity-connections
- Built by Modify — 2026 modular cost guide — reports electricity, water, sewer and telecommunications connections at approximately A$7,600–$30,600 depending on location, and septic systems on rural blocks commonly A$15,300–$38,200. Builder-published commercial guidance, not independent survey data. builtbymodify.com.au/blogs/modular-home-cost
- Eco Septic — Step-by-step guide to council approval for septic and AWTS — a site and soil evaluation informs a detailed system design showing tank location and specifications, land application area layout and size, and load calculations, demonstrating compliance with AS/NZS 1547:2012 and council policy. The application package typically includes the council application form (often titled 'Application to Install a Human Waste Treatment Device' or similar), the site and soil evaluation report and the system design plans. Commercial guidance. ecoseptic.com.au/your-step-by-step-guide-to-council-approval-for-septic-systems-awts/
- MyConnect — Explaining electricity connection fees — energy distributors charge for the initial connection when first connecting to an existing connection, typically in the range of A$10 to $60, alongside a fixed network service charge of around A$1 a day. Commercial connection-service guidance. myconnect.com.au/post/electricity-connection-fees/
- TasNetworks — Connection fees schedule — creation of a National Metering Identifier for a new connection is A$49.23 excluding GST. TasNetworks offers 16 types of basic connection services with model standing offer terms, including options such as installation of a crossover pole with overhead or underground service in single or multi phase, and solar connections up to 30 kW. Fees reflect average travel time, on-site time, materials and support vehicles for each connection type. Network-operator published fee schedule. tasnetworks.com.au/connections/fees
Figures are as published by the sources above at their respective dates and are paraphrased summaries, not verbatim reproductions. Verify current pricing and rules directly with builders, lenders and planning authorities.